Jindal’s Bank Financing Moves Mmamabula Power Project Forward

India’s Jindal Power has secured an eight-year loan of approximately US$500 million from three Indian banks for its Mmamabula energy project in Botswana, bringing the development closer to its planned financing target of US$1 billion. A further US$500 million is expected to be raised in the coming months.

The loan has been provided by Axis Bank, ICICI Bank and the Export-Import Bank of India. The project is being developed by Jindal Energy (Botswana), a subsidiary of Jindal Power, with electricity intended for sale to state-owned Botswana Power Corporation (BPC). The financing was confirmed in a 17 November 2026 announcement by JSA Advocates & Solicitors, which advised the project company. The announcement outlines funding for two project phases but does not clarify how the latest facility relates to earlier financing disclosures.

In March, lender-side law firm Shardul Amarchand Mangaldas announced that financing of up to US$1 billion had been arranged, with documents for a US$507.5 million first phase executed by a seven-bank consortium. The consortium included Axis Bank, ICICI Bank and Exim Bank, alongside four other Indian lenders.

Bloomberg separately reported a loan of approximately US$470 million with a nine year term, citing people familiar with the matter. The latest legal announcement puts the facility at approximately US$500 million, with an eight year repayment period. It remains unclear whether these disclosures refer to the same facility or different stages of the financing.

The project is expected to contribute to Botswana’s efforts to expand domestic electricity generation and reduce reliance on imported power. Electricity demand is growing by approximately 5% annually, according to remarks made by the minerals and energy minister to Parliament in March. Imports and rotational load-shedding are expected to remain necessary when required until additional generation capacity comes online.

However, publicly available project information presents differing figures for Mmamabula’s planned capacity and delivery schedule. BPC lists Jindal’s commitment as two 300 MW coal-fired power plants under power-purchase agreements. Jindal’s project website describes a 700 MW net facility and sets a December 2026 commissioning target.

Botswana’s 2026 Budget, meanwhile, refers to a 600 MW Mmamabula power plant, with the first 150 MW expected by December 2026 and full capacity targeted by June 2029. The available disclosures do not explain the differences in capacity or commissioning timelines. The development forms part of a wider effort to strengthen the country’s electricity supply. Botswana’s 2026 Budget also sets out plans to add 1.5 GW of renewable energy capacity by the first quarter of 2027.

With half of the stated US$1 billion financing target now covered by the latest loan announcement, the outstanding funding requirement and the reconciliation of project capacity and delivery timelines remain important considerations as Mmamabula advances towards construction and commissioning.